Monte Carlo Forecasting

From Kanban, #NoEstimates

Forecast delivery dates from past throughput instead of estimating every item.

Meeting time noneLearning curve Some practice

Helps with

unpredictable deliverymeeting overload

How to start

Use ten or more weeks of throughput data and answer in ranges: “85% likely by 14 March”.

It’s working when

Estimation meetings shrink and forecasts get more accurate.